Percy Preist School Project

Hello everyone, 

I just received notice from the Percy Priest Project Manager that they will beginning blasting at the school site in the very near future. I was also advised that all pre blasting surveys have been completed. Even though proper protocols are in place and followed, we strongly encourage residents to get your own surveys done to protect your interests. Although, we do not expect any issues, it is always better to insure everything is documented well before blasting commences. If you think your home should have been on the survey list, but haven't been notified, please contact the representative listed below as soon as possible. 

Listed below are scheduled construction activities.

  • Mon 10/23 - Drilling to start behind the school.
  • Fri 10/27 - Anticipated first blast around 3:30PM.
  • Mon 10/30 - Expected to start two blasts per day through the end of December. First blast will be around 11:00AM-12:00PM and second blast will be around 3:30PM-4:30PM.

Metro Nashville has also provided a link to follow construction progress of the school. Just click on the link below.

Percy Priest School Construction Progress

Any issues or concerns can be reported directly to the superintendent of the site. His information is listed below for your reference. 

Email: info@americanconstructors.us